Pembury Farnham

Current
Project highlight View gallery

Key Information

  • Sector:Industrial & Logistics
  • Size:150,800 sq ft GIA across three units (Unit 1: 59,400 sq ft; Unit 2: 20,000 sq ft; Unit 3: 71,400 sq ft), plus a 77,972 sq ft (1.79 acres) gross external storage yard
  • Client:Pembury
  • Location:Water Lane, Farnham, GU9 9GJ
  • Architect:AJA Architects LLP
  • Engineer:Burrows Graham
  • Project Manager / Employer's Agent:Knight Webb Limited
  • Principal Designer:CDM Contract Services
  • BREEAM:Excellent
  • EPC:Targeted A

Project Overview

Design and build of a high-quality, multi-unit industrial and logistics development situated on Water Lane in Farnham. The project comprises the construction of three modern, single-storey warehouse and production units (Units 1, 2, and 3) totalling 150,800 sq ft, alongside a substantial external storage yard with a gross area of 1.79 acres (77,972 sq ft).

Delivering flexible, premium logistics space, including customised elements for incoming tenant Storage King, the development combines robust operational capabilities with strong environmental performance, featuring a high-capacity solar PV system, comprehensive embodied carbon management, and Excellent BREEAM certification.

Scope of Works

  • Multi-phase delivery: Construction of three industrial units (Units 1, 2, and 3) with integral two-storey office accommodation for Units 1 and 3.
  • External storage yard: Dedicated 1.79-acre (77,972 sq ft) gross external yard facility, incorporating 1.19 acres (51,836 sq ft) of net storage area and a 0.34-acre (14,810 sq ft) dedicated access road.
  • Programme duration: 47 weeks.
  • Tenant customisation: Bespoke structural and floor slab adaptations for Storage King in Unit 2.
  • Substructure: Under croft design integration with full gas membrane protection, supported by Vibro and VSC ground improvement piling.
  • Superstructure & clearances: Haunch heights of 12 metres for Units 1 and 3, and 12.6 metres for Unit 2.
  • Infrastructure: Complex below-ground works including four large-scale attenuation tanks and feature retaining walls.
  • Highways: Associated Section 278 off-site highway and junction improvements, including permanent access from the existing Water Lane bell mouth.